Case Study

How Architectural BIM and MEP BIM Modeling Helped Save ~$350,000 on a Residential Care Facility Project

A BIM case study showing how United-BIM’s architectural and MEP BIM modeling helped a 60,000 SQFT residential care facility improve coordination, reduce rework, and save approximately $350,000.

Respite and Residential Center Main Entrance in Sunrise Florida MEP BIM Modeling project united-bim
Respite and Residential Center Children’s Outdoor Play Area in Sunrise Florida United-bim project image
Respite and Residential Center Exterior and Main Entry in Sunrise Florida project by united-bim
PROJECT TYPE
Respite and Residential Care Facility
LOCATION
Sunrise, Florida
SERVICE PROVIDED
Architectural BIM Services | MEP BIM Modeling Services
SOFTWARE USED
Autodesk Revit | AutoCAD
APPROX. PROJECT AREA
60,000 SQFT
LOD
LOD 300
CORE FOCUS
Building layout, exterior geometry, residential spaces, community areas, ceiling zones, and MEP system coordination
Requirement

Project Requirement

The construction team needed a coordinated BIM model that could bring the facility’s architectural layout and MEP systems into one reliable project environment.

The project included residential care spaces, respite areas, activity zones, support rooms, landscaped outdoor areas, circulation paths, entry canopy elements, façade features, and building systems. These areas had to be reviewed together because small coordination gaps between architecture and MEP systems could quickly lead to field changes, rework, and installation delays.

The core requirements included:
  • Architectural BIM modeling for building layout, envelope, rooms, façade, and exterior elements
  • MEP BIM modeling for HVAC, plumbing, electrical, and fire protection systems
  • Coordinated model views for design and construction review
  • Clear ceiling-space visibility for MEP routing
  • Better alignment between room planning, service zones, and system layouts
  • Reduced field conflicts during construction
Problem

The Problem We Solved

The biggest risk was not the size of the project. It was coordination across multiple space types.

Residential care rooms, activity spaces, support areas, corridors, landscaped zones, and service areas all had different functional requirements. MEP systems had to be routed without disrupting room layouts, ceiling heights, access zones, or architectural intent.

In 2D drawings, many of these relationships were difficult to review together. The construction team needed a model that made conflicts visible before they became site issues.

01
United BIM’s Approach

Developed the Architectural BIM Model

United-BIM created a Revit-based architectural model covering the building layout, walls, doors, windows, roof elements, entry canopy, façade features, and exterior massing.

The model helped the team review:

  • Residential care spaces
  • Community and activity areas
  • Circulation paths
  • Support rooms
  • Entry and drop-off zones
  • Building envelope conditions
  • Exterior architectural elements
02
United BIM’s Approach

Developed the MEP BIM Model

United-BIM modeled the major MEP systems based on project inputs and coordination requirements.

The MEP model included:

  • HVAC duct routing
  • Plumbing routes
  • Electrical pathways
  • Fire protection inputs
  • Equipment zones
  • Ceiling service areas
  • Service access points
03
United BIM’s Approach

Coordinated Architecture with Building Systems

The architectural and MEP models were reviewed together to identify areas where system routing could affect ceilings, room layouts, corridors, support spaces, and service areas.

This helped the team address coordination issues before they reached the field.

04
United BIM’s Approach

Prepared Review-Ready Model Views

United-BIM prepared focused model views for architectural review, MEP routing review, ceiling-space checks, and documentation support.

These views helped the construction team make faster decisions without relying only on disconnected drawings.

Focus Areas

Key Coordination Areas

Residential Care Areas

Reviewed room layouts, ceiling zones, and MEP routing to reduce conflicts in occupied-use spaces.

Activity and Community Spaces

Coordinated open areas, circulation paths, and system routing to maintain clean functional layouts.

Entry and Exterior Zones

Modeled canopy, façade elements, entrance geometry, and exterior architectural features for better design review.

Ceiling Service Zones

Reviewed HVAC, plumbing, electrical, and fire protection routing against architectural layouts and ceiling conditions.

Support Rooms and Back-of-House Areas

Coordinated service-heavy areas where equipment, access, and routing needed better model visibility.

Challenges and United-BIM’s Approach

Project Challenges and Our Approach

Challenges
United-BIM’s Approach
  • Multiple space types had different planning and service needs
  • Organized the architectural model by residential, community, support, and circulation zones
  • MEP routing had to work around room layouts and ceiling constraints
  • Modeled HVAC, plumbing, electrical, and fire protection routes against architectural layouts
  • Coordination gaps were difficult to detect in 2D drawings
  • Reviewed architectural and MEP systems together in a coordinated model environment
  • Field teams needed clearer construction reference views
  • Prepared focused Revit views for layout, ceiling zones, routing, and documentation support
Outcome

Results at a Glance

Estimated avoided construction cost
~$350,000
Project area modeled
60,000 SQFT
Disciplines modeled
Architecture + MEP
Coordination issues identified before field work
300+
Drawing review efficiency improvement
~28%
Ceiling-space coordination improvement
~35%
Model-based review views prepared
75+
Coordination issues identified before field work
300+
Major building zones reviewed
Residential, community, support, exterior, and service areas
Rework risk reduction
~32%
$350,000 Savings Achieved

How the $350,000 Savings Was Achieved

The estimated savings came from avoiding field rework, reducing drawing interpretation gaps, and identifying coordination issues before construction activity advanced.

The largest cost-risk areas were:

  1. Ceiling rework caused by MEP routing conflicts
  2. Architectural changes caused by late system coordination
  3. Installation delays from unclear service-zone planning
  4. Repeated drawing reviews due to disconnected information
  5. Field modifications around support rooms, corridors, and occupied-use areas

By resolving these issues in the model, the construction team reduced avoidable corrections and improved installation readiness.

Deliverables

Key Deliverables

  • Architectural BIM model
  • MEP BIM model
  • Building envelope model
  • Entry canopy and façade model elements
  • Residential area model views
  • Community space model views
  • Documentation support views
  • HVAC routing model
  • Plumbing routing model
  • Electrical pathway model
  • Fire protection model inputs
  • Ceiling-space coordination views
  • Updated Revit model files
Outcome

Project Outcome

United-BIM delivered coordinated architectural and MEP BIM models that helped the construction team review the facility as one connected building environment.

The model improved visibility across residential spaces, community areas, corridors, support rooms, exterior features, ceiling zones, and MEP systems. Instead of reviewing architecture and building services separately, the team could study how the facility worked as a complete project.

The result was better coordination, fewer field assumptions, stronger documentation control, and approximately $350,000 in avoided construction costs.